Westcoast Energy Inc.

Critical Notice

Curtailment - Pipeline

 

Notice:

 #57512

Revision: 

 #0

 

Subject:

Huntingdon/4B South Capacity for November 16 ID3, 2023 REVISED

 

Summary:

Huntingdon/4B South Capacity for November 16 ID3, 2023 REVISED

Further to Notice #57502, Westcoast will be decreasing the following flow on T South:
 
Huntingdon Delivery Area Capacity

November 16, 2023:       2,152,916 GJ 


Station 4B South Capacity

November 16, 2023:       2,345,545 GJ   

Changes in operating conditions may result in the capacity being recalled on any gas cycle.


If you have any questions, please contact the CSR hotline at (403) 699-1800.   

 
Posting Date:16-Nov-2023 16:29 CCT
Effective Date:16-Nov-2023
End Date:16-Nov-2023
Response Date:N/A
Location:N/A
Contacts:N/A