Huntingdon/4B South Capacity for September 19 - 20, 2023

 

Summary:

Huntingdon/4B South Capacity for September 19 - 20, 2023

Further to Notice #57118 (Operationally Available Capacity for September 2023), Westcoast will be allowing the following flow on T South:

Huntingdon Delivery Area Capacity

September 19, 2023:        1,189,769 GJ 

September 20, 2023:        1,586,359 GJ
 


Station 4B South Capacity

September 19, 2023:        1,993,147 GJ

September 20, 2023:        1,993,147 GJ   

The constraint is below Firm Contracted Capacity. Shippers can access the Firm Shipper Share Report for more detailed information.

Changes in operating conditions may result in the capacity being recalled on any gas cycle.


If you have any questions, please contact the CSR hotline at (403) 699-1800.   

 
Posting Date:18-Sep-2023 07:28 CCT
Effective Date:18-Sep-2023