Westcoast Energy Inc.

Critical Notice

Curtailment - Pipeline

 

Notice:

 #56799

Revision: 

 #0

 

Subject:

Huntingdon/4B South Capacity for June 2-5, 2023

 

Summary:

Huntingdon/4B South Capacity for June 2-5, 2023

Further to Notice #56792 (Operationally Available Capacity for June 2023 Revised), Westcoast will be allowing the following flow on T South:

Huntingdon Delivery Area Capacity

June 2-5, 2023:             1,858,306 GJ

Station 4B South Capacity

June 2, 2023:             1,359,736 GJ

June 3-5, 2023:          1,416,392 GJ
 
The constraint is below Firm Contracted Capacity. Shippers can access the Firm Shipper Share Report for more detailed information.

Changes in operating conditions may result in the capacity being recalled on any gas cycle.


If you have any questions, please contact the CSR hotline at (403) 699-1800. 

 
Posting Date:02-Jun-2023 08:19 CCT
Effective Date:02-Jun-2023
End Date:05-Jun-2023
Response Date:N/A
Location:N/A
Contacts:N/A