Westcoast Energy Inc.

Critical Notice

Curtailment - Pipeline

 

Notice:

 #56526

Revision: 

 #0

 

Subject:

Huntingdon/4B South Capacity for February 4 - 6, 2023

 

Summary:

Huntingdon/4B South Capacity for February 4 - 6, 2023

BC Pipeline will be allowing the following flow in T South:

Huntingdon Delivery Area Capacity

February 4 - 6, 2023:       2,124,588 GJ

Station 4B South Capacity

February 4 - 6, 2023:      2,258,862 GJ

Changes in operating conditions may result in the capacity being recalled on any gas cycle.   
 
 
   


If you have any questions, please contact the CSR hotline at (403) 699-1800. 

 
Posting Date:03-Feb-2023 07:56 CCT
Effective Date:03-Feb-2023
End Date:07-Feb-2023
Response Date:N/A
Location:N/A